For a cafe, the cost of a repaint is not just the painter's invoice. It is the days you cannot trade, or the days you trade badly with a smell of paint in the air. Good planning cuts both. The aim is simple: do the job when you would be shut anyway, and be able to open on time with the premises clean.
This guide is about sequence and timing. For what to check about the finish itself, including surfaces and lead in older paint, see the separate article on repainting a cafe or shop interior.
Work backwards from your quiet periods. Public holidays, the days between Christmas and New Year, a slow week in winter, or a regular closed day are all candidates. Look at your own sales records and supplier orders to find when stock and staffing are lowest.
Then ask the painter how many working days the job needs, including drying and a second coat. A good quote will separate preparation, painting and cure time. Preparation is often the longest part, and some of it, such as moving fixtures and patching, can happen before the main closure.
If you cannot close fully, split the job. Paint the dining area one week and the kitchen and back-of-house the next, or do half of a long wall at a time. It takes longer overall, but it keeps some revenue.
Food areas are the sensitive ones. Dust and fumes have no business near open food, and MPI's template food control plan says to limit dust, dirt, fumes and pests entering buildings used for handling, making or storing food. A practical rule is that if food is being made, stored or served in the space, it is not a painting zone at that moment.
You might be able to keep trading from a takeaway window or a front counter while the back is painted, but only if you can keep food, equipment and packaging well away from the work and keep the fumes out. Be honest about whether that is possible. A takeaway that smells of fresh paint and has dust on the pie warmer is worse than a closed sign.
In the days before the painters arrive:
Painters bring tins, thinners, brushes and sometimes sprayers. Decide beforehand where these will be stored overnight. WorkSafe's guidance on storing hazardous substances says to store only what you need, to keep lids on containers to hold vapours in, and to follow the safety data sheet for storage and incompatibility. It also warns that containers used for hazardous substances should not usually be ones that contain food or drink, or that could be mistaken for them. That includes your own food containers: do not let anyone decant paint into a kitchen tub.
Under MPI's template, maintenance compounds and chemicals must be fully labelled, stored, sealed and used per manufacturer's instructions, and kept in containers clearly different from food containers. Agree a storage spot with the painter, away from food and food equipment, and lock it if you can.
Paint fumes linger. The Building Performance site explains that water-based products produce less solvent than solvent-based ones, although water-based acrylics can still contain volatile organic compounds, and that polyurethane can give off compounds for years. If you are choosing between products, ask which suits a space you will reopen quickly, and what ventilation they need.
Do not assume that a surface which feels dry is ready for food. Ask the painter for the product's recoat and cure guidance and follow it.
Allow time at the end of the job. MPI's pest control guidance, which deals with treatments carried out in food areas, says the area must be adequately ventilated, cleaned and sanitised before operations restart. A repaint is the same in principle. Dust settles on shelving, inside equipment and on food-contact surfaces, even when you thought you had covered everything.
The template says cleaning removes dirt and grease and sanitising kills remaining bugs, and that you cannot sanitise until you have cleaned. After a repaint, plan on:
Build that half day, or full day for a big kitchen, into the schedule so you do not have to rush it.
Staff need to know which areas are out of bounds and when, and where chemicals are kept. Suppliers need to know about access if you are closed. Your landlord may need notice. If your food business is verified, a heads-up to your verifier about the work is sensible, particularly if the job involves moving equipment or changing how food flows through the premises.
Ask your painter for a written plan that shows the sequence, the areas, the products, the drying times and what they expect from you. Firms experienced with planning a commercial repaint around trading hours will usually have a standard way of doing this, and it is worth asking to see it. Eggshell & Co publishes planning notes for commercial repaints that you can read before you ask for a quote.
Whoever does the work, aim to agree three things in writing: the finish date, who is responsible for cleaning up, and what happens if a delay pushes into your trading time.